Mt Marion flotation plant and underground development FID

Mineral Resources (MinRes) has announced a Final Investment Decision to significantly expand its Mt Marion lithium operation, in partnership with joint venture partner Jiangxi Ganfeng Lithium Co Ltd (Ganfeng).

Published on 26 May 2026

Drone image of Mt Marion lithium mine site
Drone image of Mt Marion lithium mine site

The expansion – which includes the construction of a new flotation plant and the development of underground mining – represents a total capital investment of $490 million (100% basis), to be deployed across FY27 and FY28.

The investment breaks down across three key areas: a flotation plant ($240M), underground pre-production development ($220M) and non-processing infrastructure ($30M).

At the current spot spodumene price of approximately US$2,700/t SC6, the payback period is expected to be less than one year¹.

The flotation plant and underground mining program are expected to deliver meaningful improvements to the Mt Marion operation, supporting mine life through access to additional mineral resources below the existing open pit.

The projects will also guide improved plant recoveries, targeting approximately 70%, increased installed capacity from ~500ktpa SC6 to 600ktpa SC6 and remove the lower-grade SC3.5 product to deliver a single SC5 product.

Tendering for an underground mining contractor is already underway, with central underground development expected to commence in Q1 FY27.

From FY28, Mt Marion will operate as a combined open pit and underground mine, with underground ore from open stoping expected to supplement up to 40% of processing feed.

The flotation circuit will be built alongside the existing dense media separation plant to recover fine spodumene currently lost to tailings, constructed and operated by MinRes' Mining Services division. Construction is targeted to begin in Q1 FY27, with commissioning and ramp-up scheduled for 2H FY28.

Minimal disruption to existing operations is expected during construction and commissioning. The site's accommodation camp will also be expanded from 500 to 750 rooms to support both projects.

MinRes Managing Director Chris Ellison welcomed the decision.

"This high-return brownfield investment sets up Mt Marion for decades to come. Underground mining and flotation will work together to access deeper high-grade ore, lift recoveries and produce a single 5% product,” Ellison said.

"I thank our partner Ganfeng for their collaboration on the design and commitment to these projects, which will ensure we unlock the full potential of Mt Marion."

Learn more about the MinRes Lithium business.

¹ Payback period based on current spot spodumene price of approximately US$2,700/t SC6.

Lithium

View All
truck driving at lithium mine site mt marion
LithiumLeadership of Lithium division

Following the recent announcement of Joshua Thurlow’s resignation as Chief Executive Lithium, MinRes has confirmed current executive Darren Hardy will assume leadership of the division.

14 October 2026
Thomas Cuthbert, Claudia McGrath, Corey Chalmers
Mining ServicesMinRes supports next generation of seafarers

Mineral Resources’ (MinRes) marine operation has established itself as an innovator in the industry since operations began in 2024. Now the business is developing the next generation of seafarers through the MinRes Marine Cadet Program.

12 October 2026
Isla Wagstaff and mum Ashleigh Evans, with MinRes Director People Andrea Chapman and Lead Sonographer Marilyn Zelesco at Fiona Stanley Hospital's new paediatric ultrasound suite
PartnershipsMinRes funds paediatric ultrasound suite

Mineral Resources (MinRes) is proud to have funded a new dedicated paediatric ultrasound suite at Fiona Stanley Hospital through its partnership with Telethon.

8 October 2026

Get in touch

For all media related inquiries, contact our Media Manager.